Duval County Screen Enclosure Permit Timeline
Beta estimate from published county-level data — not yet from live Cleard pipeline data for Duval County specifically.
Why a screen enclosure permit takes 11–18 days in Duval County
Duval County and the City of Jacksonville operate under a consolidated city-county government — permits are issued through the City of Jacksonville Building Inspection Division rather than a separate standalone county building department.
What reviewers check on a screen enclosure submittal
Screen enclosures are reviewed primarily for wind-load rating on the frame and attachment details — typically a lighter review than a full structural package, which is why the range is shorter than a building permit in the same county.
Tired of waiting 11–18 days? Cleard runs private-provider plan review in Duval County — 2-day plan review, same-day inspections.
See Cleard in Duval County →Other permit timelines in Duval County